Present Status of The Barrages Projects
Sr. # |
River |
Name of Barrage |
Status |
1 |
Indus |
Taunsa |
- Project completed in December 09, 2009 (Financed by World Bank & JICA Grant-in-Aid)
- Expenditure incurred Rs. 11,232 million.
|
2 |
Jinnah |
- Works under ICB contract commenced on June 18, 2012 and completed on November 15, 2015; WRMIS & DSS developed. Bathymetric equipment (8 Sets) provided at barrages;
RTFM System installed at key points and Eastern Sadiqia Canal System; Calibration in process.
|
3 |
Chenab |
Khanki |
- Works under ICB contract commenced on July 08, 2013 and completed on August 15, 2017; New state-of-the-art barrage with allied works is operational; Integration and final commissioning of ICTS works underway.
|
4 |
Trimmu |
- Works under ICB contract commenced on May 05, 2016; works in progress.
- Stage-I civil works in left half of barrage completed.
- Stage-II works in right half of barrage in progress.
- Haveli canal, TS Link canal head regulator gates and barrage gates (1-27) in left half replaced. Barrage gates replacement in right half of barrage in progress.
- Installation of hoisting systems and LCPs underway.
- Construction of additional bays and allied works in progress.
- Strengthening of LMB and RMB in progress.
|
5 |
Panjnad |
- Award of contract in process.
|
6 |
Ravi |
Balloki |
- Rehabilitation and up-gradation of Balloki Barrage is in progress under PIAIP as part of LBDCIP.
- Physical works under ICB contract in progress.
|
7 |
Sutlej |
Sulemanki |
- Works under ICB contract commenced on July 08, 2014; Works in progress.
- Upstream floor added with sheet piles at its upper end; strengthening of floors done; bela substantially removed; gates of left pocket (8 nos.) and right pocket (8 nos.) replaced; main weir (24 nos.) gates rehabilitated; Electrification and building works are in progress.
|
8 |
Islam |
- Feasibility study (2005) and Detailed design(2009) completed.
- PC-I is pending for arrangement of finances.
|
Page updated on March 02, 2021