Present Status of The Barrages Projects

Sr. #
River
Name of Barrage
Status
1
Indus
Taunsa
  • Project completed in December 09, 2009 (Financed by World Bank & JICA Grant-in-Aid)
  • Expenditure incurred Rs. 11,232 million.
2
Jinnah
  • Works under ICB contract commenced on June 18, 2012 and completed on November 15, 2015; WRMIS & DSS developed. Bathymetric equipment (8 Sets) provided at barrages; RTFM System installed at key points and Eastern Sadiqia Canal System; Calibration in process.
3
Chenab
Khanki
  • Works under ICB contract commenced on July 08, 2013 and completed on August 15, 2017; New state-of-the-art barrage with allied works is operational; Integration and final commissioning of ICTS works underway.
4
Trimmu
  • Works under ICB contract commenced on May 05, 2016; works in progress.
  • Stage-I civil works in left half of barrage completed.
  • Stage-II works in right half of barrage in progress.
  • Haveli canal, TS Link canal head regulator gates and barrage gates (1-27) in left half replaced. Barrage gates replacement in right half of barrage in progress.
  • Installation of hoisting systems and LCPs underway.
  • Construction of additional bays and allied works in progress.
  • Strengthening of LMB and RMB in progress.
5
Panjnad
  • Award of contract in process.
6
Ravi
Balloki
  • Rehabilitation and up-gradation of Balloki Barrage is in progress under PIAIP as part of LBDCIP.
  • Physical works under ICB contract in progress.
7
Sutlej
Sulemanki
  • Works under ICB contract commenced on July 08, 2014; Works in progress.
  • Upstream floor added with sheet piles at its upper end; strengthening of floors done; bela substantially removed; gates of left pocket (8 nos.) and right pocket (8 nos.) replaced; main weir (24 nos.) gates rehabilitated; Electrification and building works are in progress.
8
Islam
  • Feasibility study (2005) and Detailed design(2009) completed.
  • PC-I is pending for arrangement of finances.
Page updated on March 02, 2018